Saudi Arabia awards 2GW/8GWh of battery storage in $1.16 billion tender

·

The Saudi Power Procurement Company (SPPC) has awarded four battery energy storage contracts totalling 2GW/8GWh, with a combined value of SAR4.35 billion, about US$1.16 billion. The awards, announced on 20 August 2026, are the first made under a government build-own-operate (BOO) model in Saudi Arabia, with each project sized at 500MW with four hours of duration and backed by a 15-year service contract.

Three of the projects, Haden and Al-Muwayh in Makkah province and Al-Khahfah in Hail province, went to a consortium of Saudi Energy, ACWA Power and Al Sharif Contracting and Commercial Development Company, with Larsen & Toubro taking the engineering, procurement and construction role across their combined 6GWh. The fourth, Al-Khushaybi in Qassim province, was won by Engie with Haji Abdullah Alireza & Co, at a reported investment of around US$220 million.

Why does this award matter?

It sets a market price for firm, four-hour storage in the Gulf. The contract value works out at roughly US$145 per kWh of installed capacity, and the BOO structure, with operators keeping 100 percent equity, shows Riyadh trusting private balance sheets to own grid infrastructure rather than procuring it as EPC.

The award also confirms how quickly Saudi Arabia has become one of the largest storage buyers outside China and the United States. SPPC qualified 33 bidders for the programme in January 2025, launched a second 3GW/12GWh tender in April 2026, and by early 2026 the kingdom had roughly 37GWh of battery capacity announced, in construction or in operation. Storage underpins the Vision 2030 goal of meeting half of Saudi electricity demand from renewables by the end of the decade.

What happens next?

The four consortia move to financial close and delivery, with Larsen & Toubro building out three of the sites. Bids in the second, larger tender are the one to watch: if pricing falls again, the Gulf BOO model will become the reference structure for storage tenders across the Middle East and North Africa.

Sources: Energy-Storage.news, reporting the SPPC award of 20 August 2026.

Like this?

Add EnergiTech Media as a preferred source and Google shows our stories first in Top Stories.

Keep reading

More big stories

All news →

Before you go

Get the big stories in your inbox

One email a week with the stories worth reading. Free, and easy to leave.

The newsletter

The week’s big stories, in one email

What mattered, why it mattered, and one thing to argue about at lunch. Free, weekly, no paywall.

Just your email. Unsubscribe any time.